Lewallen Bridge Update
5/11/20 LEWALLEN BRIDGE REPLACEMENT PROJECT UPDATE Lynn Murphy (Project Coordinator) At month 21 of the 36 month project: Girder Beam Installation: Girder beam work continues, and twenty-seven additional beams are arriving this week. Once these are installed, only nine more are needed, and will be set once abutment # 1 is ready. Structures: Abutment #…