Lewallen Bridge Replacement Update – June 23, 2020
LEWALLEN BRIDGE REPLACEMENT PROJECT UPDATE Lynn Murphy (Project Coordinator) At month 22 of the 36 month project: Structures: Abutment # 1: After several months of delays, construction will proceed this week on the north abutment. Precast concrete sections will be installed around the existing steel beam pilings to create the structure (as opposed to building…