Lewallen Bridge Replacement Update – July 20, 2020
LEWALLEN BRIDGE REPLACEMENT PROJECT UPDATE Lynn Murphy (Project Coordinator) At month 23 of the 36 month project: Structures: Abutment # 1: Good progress has been made during the past four weeks. A visiting crew was assigned to this structure alone and they have installed the engineered walls and the compacted crushed stone backfill. Work will…