Lewallen Bridge Replacement Project Update 8-17-20
Lynn Murphy (Project Coordinator) At month 24 of the 36-month project: Structures: Abutment #1: This structure has been built and is now supporting the last nine girder beams. The existing steel beam pilings were wrapped with rebar, concrete forms were placed, and concrete was poured to create the abutment. The last nine girder beams were…