12/14/20
LEWALLEN BRIDGE REPLACEMENT PROJECT UPDATE
Lynn Murphy (Project Coordinator)
At month 28 of the 36-month project
Concrete Bridge Deck –
The bridge deck concrete pouring construction began on November 24, 2020, and about 20% of the deck has been poured. A completion date for this phase of the bridge project will depend on the upcoming winter weather. Read more…