July 16, 2019
LEWALLEN BRIDGE REPLACEMENT PROJECT UPDATE
Lynn Murphy, Project Coordinator
Month 11 of the 36 month project:
Underground utility relocation: The existing natural gas, sanitary sewer, and water lines that created a conflict with proposed structures have now been replaced and relocated, and the underground utility phase is complete. This has allowed construction on the remaining five columns for piers # 1, # 2, and # 3 to being. Visit: www.clintontn.net/BridgeProjUpdate.htm for photos.